A1 Scotswood to North Brunton – Major Highways Works
ABOUT THE PROJECT
A complex and evolving highways project delivered under a tight completion schedule.
A complex and evolving highways project delivered under a tight completion schedule. The scope included over 10,000m of drainage using pipes from 150mm to 1200mm, construction of more than 200 manholes and catchpits, 1,500m of kerb drain, and 9,000m of filter drains—all completed within lane closures and nightshifts. Despite changing project demands, the team maintained high standards and met critical deadlines.